After years of planning and discussions, Liberty County is moving forward with construction plans for a new county jail.
During a special called meeting Friday, Oct. 30, Liberty County Commissioners Court voted unanimously to proceed with an approximately 500-bed facility, choosing not to pursue a larger 600-bed option that would have provided additional room for the county’s growing detention needs.
The county already has funding available for the 500-bed facility, making Friday’s decision an important step toward getting the long-awaited project underway.
Although county officials recognize the need for a larger jail, the additional cost of a 600-bed facility has been a major consideration. With the funding for the smaller facility already in place, commissioners opted to move ahead rather than pursue the more expensive alternative.
Friday’s meeting focused on two items related to advancing the project. The first involved selecting specifications for subcontractor bidding.
Commissioners were presented with two choices. One would allow the county to seek bids based on a 500-bed jail, while the other would allow alternative bids for either a 500-bed or 600-bed facility.
After spending approximately 50 minutes in executive session, commissioners returned to open court and approved the 500-bed option.
Pct. 1 Commissioner Bruce Karbowski made the motion, which was seconded by Pct. 4 Commissioner Gerald Kolarik.
The decision moves the county closer to replacing its aging jail, which has struggled with maintenance issues and insufficient bed space. Those problems have forced Liberty County to house some inmates in facilities operated by other agencies across Texas.

Commissioners also took action Friday to begin the process of selecting someone to oversee the construction project.
The court voted to solicit qualifications or proposals for project management services, with the county’s purchasing department handling the process.
During the discussion, a commissioner initially suggested that Liberty County’s fire marshal, Nathan, be considered for the position. However, concerns were raised that specifically naming a county employee in the motion could create the appearance of favoritism.
The motion was revised to remove that language before commissioners approved it.
The county is not obligated to hire an outside project manager. Commissioners will review the responses and determine how to proceed.